Cambridge O Level Accounting 7707 · 5.5 Manufacturing accounts

Q157 · 7707/13/O/N/21 Q25

Worked solution from the Preparation of financial statements MCQ booklet.

Q1577707/13/O/N/21original Q25Multiple choice
Question 25 from 7707/13/O/N/21

Worked solution

The question asks how an increase in work in progress changes cost of production and cost of sales.

Cost of production = factory cost + opening work in progress − closing work in progress. If work in progress rises, a bigger amount is taken off, so the cost of production decreases.

The cost of production goes into cost of sales, so a lower cost of production also makes the cost of sales decrease.

So the answer is A.

B says no effect on cost of sales, but it takes its figure from cost of production. C and D say cost of production increased, which is the wrong way round.

KEY IDEAClosing work in progress is taken off the cost of production, so a rise in work in progress lowers it, and cost of sales falls with it.
ANSWER A
VIDEO
▶ Starts at Q25 (35:55)

Starts at Q25 (35:55) · by Sir Waleed Khanzada. Tap the picture to open it on YouTube.

Solutions follow the official Cambridge mark schemes. Videos are from other YouTube channels. Paper codes read component / series / year: M/J = May/June, O/N = October/November. Past-paper questions © UCLES, reproduced for classroom practice.