Cambridge A2 Level Accounting 9706 · 4.2 Standard costing

Q25 · 9706/31/M/J/22 Q6

Worked solution from the Cost and management accounting (A Level) Theory (Paper 3) booklet, Part 2 of 4.

Q259706/31/M/J/22original Q6Structured · 25 marks
Question 6 from 9706/31/M/J/22

Worked solution

(a)

Budgeted profit = sales − all budgeted costs, for 6 000 units.

Details$
Sales (6 000 × $70)420 000
Direct materials (6 000 × $6)36 000
Direct labour (6 000 × $36)216 000
Fixed overheads72 000
Total costs(324 000) [1]
Budgeted profit96 000 [1]

(b)(i)

Sales price variance = (actual price − budget price) × actual units

= ($72 − $70) × 5 800 = $11 600 [1]

The actual price is higher, so it is favourable (F). [1]

(b)(ii)

Sales volume variance = (budgeted units − actual units) × standard profit per unit

Standard profit per unit = $70 − $6 − $36 − $12 (fixed overhead $72 000 ÷ 6 000) = $16 [1]

= (6 000 − 5 800) × $16 = $3 200 [1]

Fewer units were sold, so it is adverse (A). [1]

(b)(iii)

Direct material total variance = standard cost of actual output − actual cost

= (5 800 × $6) − $35 113 = $34 800 − $35 113 = $313 [1]

Actual cost is higher, so adverse (A). [1]

(b)(iv)

Direct labour total variance = standard cost of actual output − actual cost

= (5 800 × $36) − $221 760 = $208 800 − $221 760 = $12 960 [1]

Adverse (A). [1]

(b)(v)

Fixed overhead absorption rate = $12 ÷ 3 hours = $4 per labour hour

Fixed overhead volume variance = (budgeted units − actual units) × 3 hours × $4

= (6 000 − 5 800) × 3 × $4 = $2 400 [1]

Less was absorbed than budgeted, so adverse (A). [1]

Other method: $72 000 − (5 800 × $12) = $2 400 (A).

(b)(vi)

Fixed overhead expenditure variance = budgeted fixed overhead − actual fixed overhead

= $72 000 − $70 400 = $1 600 [1]

Actual is lower, so favourable (F). [1]

(c)(i)

Write any three likely causes of the adverse sales volume variance:

Actual sales (5 800 units) were lower than budget. [1]

The selling price was raised from $70 to $72, which may have reduced demand. [1]

Any one more: promotion or advertising was ineffective, or the quality of the goods was not as good as expected. [1]

(c)(ii)

Split the total variance into rate and efficiency. Standard rate = $36 ÷ 3 = $12 per hour.

Labour rate variance = (17 600 × $12) − $221 760 = $211 200 − $221 760 = $10 560 (A) [1]

Actual rate = $221 760 ÷ 17 600 = $12.60, so the hourly pay rate has increased from $12 to $12.60. [1]

Labour efficiency variance = [(5 800 × 3) − 17 600] × $12 = (17 400 − 17 600) × $12 = $2 400 (A) [1]

200 more labour hours were used than the standard, due to an inefficient labour force. [1]

(d)

Total variance = price variance + usage variance. The total is $313 adverse and usage is $1 275 adverse, so the price variance = $1 275 (A) − $313 (A) = $962 favourable. [1]

The material was cheaper than expected, maybe because of a change of supplier. [1]

Decision: P Limited has been successful in controlling the cost price of direct material. [1]

KEY IDEAA variance compares actual with standard; split the total into price and usage (or rate and efficiency) to find the cause.
TOTAL 25 marks

Official mark scheme

Mark scheme for 9706/31/M/J/22 question 6