Worked solution from the Cost and management accounting (A Level) Theory (Paper 3) booklet, Part 2 of 4.
Budgeted profit = sales − all budgeted costs, for 6 000 units.
| Details | $ |
|---|---|
| Sales (6 000 × $70) | 420 000 |
| Direct materials (6 000 × $6) | 36 000 |
| Direct labour (6 000 × $36) | 216 000 |
| Fixed overheads | 72 000 |
| Total costs | (324 000) [1] |
| Budgeted profit | 96 000 [1] |
Sales price variance = (actual price − budget price) × actual units
= ($72 − $70) × 5 800 = $11 600 [1]
The actual price is higher, so it is favourable (F). [1]
Sales volume variance = (budgeted units − actual units) × standard profit per unit
Standard profit per unit = $70 − $6 − $36 − $12 (fixed overhead $72 000 ÷ 6 000) = $16 [1]
= (6 000 − 5 800) × $16 = $3 200 [1]
Fewer units were sold, so it is adverse (A). [1]
Direct material total variance = standard cost of actual output − actual cost
= (5 800 × $6) − $35 113 = $34 800 − $35 113 = $313 [1]
Actual cost is higher, so adverse (A). [1]
Direct labour total variance = standard cost of actual output − actual cost
= (5 800 × $36) − $221 760 = $208 800 − $221 760 = $12 960 [1]
Adverse (A). [1]
Fixed overhead absorption rate = $12 ÷ 3 hours = $4 per labour hour
Fixed overhead volume variance = (budgeted units − actual units) × 3 hours × $4
= (6 000 − 5 800) × 3 × $4 = $2 400 [1]
Less was absorbed than budgeted, so adverse (A). [1]
Other method: $72 000 − (5 800 × $12) = $2 400 (A).
Fixed overhead expenditure variance = budgeted fixed overhead − actual fixed overhead
= $72 000 − $70 400 = $1 600 [1]
Actual is lower, so favourable (F). [1]
Write any three likely causes of the adverse sales volume variance:
Actual sales (5 800 units) were lower than budget. [1]
The selling price was raised from $70 to $72, which may have reduced demand. [1]
Any one more: promotion or advertising was ineffective, or the quality of the goods was not as good as expected. [1]
Split the total variance into rate and efficiency. Standard rate = $36 ÷ 3 = $12 per hour.
Labour rate variance = (17 600 × $12) − $221 760 = $211 200 − $221 760 = $10 560 (A) [1]
Actual rate = $221 760 ÷ 17 600 = $12.60, so the hourly pay rate has increased from $12 to $12.60. [1]
Labour efficiency variance = [(5 800 × 3) − 17 600] × $12 = (17 400 − 17 600) × $12 = $2 400 (A) [1]
200 more labour hours were used than the standard, due to an inefficient labour force. [1]
Total variance = price variance + usage variance. The total is $313 adverse and usage is $1 275 adverse, so the price variance = $1 275 (A) − $313 (A) = $962 favourable. [1]
The material was cheaper than expected, maybe because of a change of supplier. [1]
Decision: P Limited has been successful in controlling the cost price of direct material. [1]