Cambridge AS Level Accounting 9706 · 2.2 Traditional costing methods

Q16 · 9706/21/O/N/21 Q4

Worked solution from the Cost and management accounting (AS Level) Theory (Paper 2) booklet, Part 2 of 2.

Q169706/21/O/N/21original Q4Structured · 30 marks
Question 4 from 9706/21/O/N/21

Worked solution

(a)

Contribution per unit = selling price − direct material − direct labour − variable overhead.

DetailsEss $Tee $Ewe $
Selling price304369
Direct material182236
Direct labour4614
Variable overhead235
Contribution per unit61214 [3]

(b)

Contribution = contribution per unit × maximum demand. Fixed overheads per month = $96 000 ÷ 12 = $8 000.

Details$
Ess 300 × $61 800
Tee 400 × $124 800
Ewe 360 × $145 040
Maximum contribution11 640 [1]
Fixed overheads ($96 000 ÷ 12)(8 000) [1]
Maximum profit3 640 [1]

(c)

Hours per unit = labour cost ÷ $8: Ess 0.5, Tee 0.75, Ewe 1.75.

Ess 300 × 0.5 = 150; Tee 400 × 0.75 = 300; Ewe 360 × 1.75 = 630.

Total = 1 080 hours [1]

(d)

Labour is the limiting factor (900 hours, not 1 080). Rank the products by contribution per direct labour hour.

DetailsEssTeeEwe
Contribution per unit$6$12$14
Direct labour hours per unit0.50.751.75
Contribution per labour hour$12$16$8 [3]
Ranking213 [1]

Production plan: make Tee first, then Ess, then Ewe with the hours left. Hours left for Ewe = 900 − 300 − 150 = 450; 450 ÷ 1.75 = 257 units.

Details$
Tee 400 × $124 800 [1]
Ess 300 × $61 800 [1]
Ewe 257 units × $143 598 [2]
Maximum contribution10 198 [1]
Fixed overheads(8 000) [1]
Maximum profit2 198 [1]

(e)

All 1 080 hours are now worked, so 180 hours (1 080 − 900) are overtime. Premium = 25% × $8 = $2 per hour × 180 hours = $360. The bonus adds $200 to fixed overheads.

Details$
Original maximum contribution11 640
Less overtime premium(360) [1]
Total contribution11 280 [1]
Fixed overheads $8 000 + bonus $200(8 200) [1]
Total profit3 080 [1]

(f)

Write two disadvantages, each with its development (accept other valid responses):

A bonus may cause workers to rush [1]

which may affect the quality of the product. [1]

It will incur additional expenses [1]

which may not be passed on to the customer and so may reduce profit. [1]

(g)

Write two disadvantages, each with its development (accept other valid responses):

Budgets are based on estimates which may be inaccurate [1]

leading to bad decision-making. [1]

Budgets may be set too high [1]

which may demotivate employees. [1]

KEY IDEAWhen labour is limited, rank products by contribution per labour hour and make the best ones first.
TOTAL 30 marks

Official mark scheme

Mark scheme for 9706/21/O/N/21 question 4
VIDEO
▶ Whole paper

Video solution of the whole paper · by Karachians Academy. Tap the picture to open it on YouTube.