9706/11/O/N/23 question 26: worked solution (October/November 2023, paper 11)
Show as plain textHide plain text
Cambridge AS Level Accounting 9706 · 2.2 Traditional costing methods Worked solution from the Cost and management accounting (AS Level) MCQ booklet. Q239 9706/11/O/N/23 original Q26 Multiple choice Worked solution The question asks for the price on the job cost sheet. Materials = $1 100 . Labour = 30 hours × $14 = $420 . Overheads = 30 hours × $10 = $300 . Total cost = $1 100 + $420 + $300 = $1 820 . Mark-up of 30% on cost = $1 820 × 30% = $546. Price = $1 820 + $546 = $2 366 . So the answer is D . A ($1 520) leaves out the overheads ($1 100 + $420). B is the total cost with no mark-up. C ($1 976) adds the mark-up to a cost that leaves out the overheads ($1 520 × 1.30). KEY IDEA Job price = total cost (materials + labour + overheads) plus the mark-up on that cost. ANSWER D VIDEO ▶ Starts at Q26 (47:16) Starts at Q26 (47:16) · by Study with Prashna. Tap the picture to open it on YouTube.