Cambridge AS Level Accounting 9706 · 2.1 Costs and cost behaviour Worked solution from the Cost and management accounting (AS Level) MCQ booklet. Q51 9706/13/O/N/22 original Q23 Multiple choice Worked solution The question asks for the total factory labour cost. Basic hours: 1000 × $10 = $10 000 Overtime hours: 1500 − 1000 = 500 hours at time and a half ($15) = $7 500 Bonus: production (15 000) is above target (12 500), so bonus = 10% × $10 000 basic pay = $1 000 Total = $10 000 + $7 500 + $1 000 = $18 500 So the answer is B . A pays all 1 500 hours at the basic rate and adds the bonus. C works out the bonus on all pay including overtime. D pays all 1 500 hours at time and a half. KEY IDEA Labour cost = basic pay + overtime + bonus. ANSWER B VIDEO ▶ Starts at Q23 (45:28) Starts at Q23 (45:28) · by Study with Prashna. Tap the picture to open it on YouTube.