Cambridge AS Level Accounting 9706 · 2.2 Traditional costing methods

Q131 · 9706/11/M/J/21 Q24

Worked solution from the Cost and management accounting (AS Level) MCQ booklet.

Q1319706/11/M/J/21original Q24Multiple choice
Question 24 from 9706/11/M/J/21

Worked solution

The question asks how under-absorption can happen. It happens when overheads absorbed are less than overheads incurred.

1 is wrong: over-budgeting overheads makes the rate too high, so more is absorbed (over-absorption).

2 is correct: under-budgeted overheads make the rate too low, so too little is absorbed.

3 is correct: if production is less than budgeted, fewer hours or units are absorbed, so too little is recovered.

4 is wrong: more production than budgeted absorbs more.

Correct: 2 and 3.

So the answer is C.

A, B and D each include 1 or 4, which cause over-absorption.

KEY IDEAUnder-absorption comes from budgeting too little overhead or producing less than budgeted.
ANSWER C
VIDEO
▶ Starts at Q24 (46:24)

Starts at Q24 (46:24) · by Study with Prashna. Tap the picture to open it on YouTube.

Solutions follow the official Cambridge mark schemes. Videos are from other YouTube channels. Paper codes read component / series / year: M/J = May/June, O/N = October/November. Past-paper questions © UCLES, reproduced for classroom practice.