Worked solution from the Cost and management accounting (AS Level) MCQ booklet.
The question asks by how much overheads are under- or over-absorbed.
Absorption rate = budgeted overheads ÷ budgeted hours = $80 000 ÷ 10 000 = $8 per labour hour
Overheads absorbed = actual hours × rate = 11 000 × $8 = $88 000
Actual overheads = $82 000
Absorbed $88 000 is more than incurred $82 000, so overheads are over-absorbed by $88 000 − $82 000 = $6 000
So the answer is A.
B has the right amount but the wrong direction. C and D ($8 000) compare the absorbed $88 000 with the budgeted $80 000 instead of the actual $82 000.