Cambridge A2 Level Business 9609 · 9.2 Quality management

Q12 · 9609/32/M/J/24 Q2

Worked solution from the Operations management Theory (Paper 3) booklet, Part 2 of 3.

Q129609/32/M/J/24original Q2Structured · 8 marks
Question 2 from 9609/32/M/J/24

Worked solution

Answer

Knowledge: total quality management (TQM) is a method of quality assurance that involves all employees in quality improvement and aims to get things right first time, with zero defects. Problems include the cost of training, resistance from employees, a change of culture and short-term falls in quality while changes are put in place.

Problem 1 (culture and training cost, application): most SF employees are on flexible contracts (temporary or zero-hour), are unskilled and have limited training. They may lack commitment to SF, so it is hard to change the culture. Each new group of temporary workers hired at harvest time will need training every year, which raises the cost of TQM.

Problem 2 (redundancy and short-term quality, application): SF now uses quality control inspectors to detect faults in final products. TQM prevents faults rather than detects them, so inspectors may become redundant. This adds costs and worries about job security, which can cut productivity. Also, quality may get worse at first while employees adjust. More ice cream and tofu may be rejected, which leaves customers dissatisfied, reduces sales and lowers profit, when the factory is already near capacity.

This earns the top band for knowledge: two relevant problems of TQM are identified. [2]

It earns the top band for application: each problem is applied to SF (flexible contracts and limited training, quality inspectors and rejected ice cream and tofu). [2]

It reaches the top band for analysis: developed analysis of two points, each linking cause, impact and consequence. [4]

KEY IDEATQM needs committed, trained staff and takes time to work, so SF's flexible-contract workforce and current inspection system make it costly and risky at first.
TOTAL 8 marks

Official mark scheme

Mark scheme for 9609/32/M/J/24 question 2
VIDEO
▶ Whole paper

Video solution of the whole paper · by Learn Business & Accounting with Azka. Tap the picture to open it on YouTube.

Solutions follow the official Cambridge mark schemes; marks are shown in grey. Videos are from other YouTube channels. Paper codes read component / series / year: M/J = May/June, O/N = October/November. Past-paper questions © UCLES, reproduced for classroom practice.