Cambridge AS Level Accounting 9706 · 2.2 Traditional costing methods

Q252 · 9706/13/O/N/23 Q26

Worked solution from the Cost and management accounting (AS Level) MCQ booklet.

Q2529706/13/O/N/23original Q26Multiple choice
Question 26 from 9706/13/O/N/23

Worked solution

The question asks which statements about over and under absorption are correct. Over absorbed means overhead absorbed is more than actual; under absorbed means it is less.

Absorbed overhead = actual activity × predetermined rate.

Statement 1: actual activity below budget means less is absorbed, so the overhead is under absorbed. Statement 1 is wrong. Statement 2 is correct.

Statement 3: actual overhead above budget means actual cost is more than what was absorbed, so it is under absorbed. Statement 3 is wrong. Statement 4 is correct.

So the correct statements are 2 and 4.

So the answer is D.

A, B and C each include statement 1 or 3.

KEY IDEALower activity or higher actual overhead than budgeted leads to under absorption.
ANSWER D
VIDEO
▶ Starts at Q26 (38:16)

Starts at Q26 (38:16) · by Study with Prashna. Tap the picture to open it on YouTube.

Solutions follow the official Cambridge mark schemes. Videos are from other YouTube channels. Paper codes read component / series / year: M/J = May/June, O/N = October/November. Past-paper questions © UCLES, reproduced for classroom practice.