Worked solution from the Cost and management accounting (AS Level) MCQ booklet.
The question asks for the actual overhead expenditure.
Absorption rate = $80 000 ÷ 5 000 budgeted hours = $16 per hour.
Overhead absorbed = 4 500 actual hours × $16 = $72 000.
Overheads were under absorbed by $12 000, which means actual overhead was more than absorbed: $72 000 + $12 000 = $84 000.
So the answer is D.
A takes $12 000 off the overhead absorbed ($72 000) and B takes it off the budgeted overhead ($80 000); both should add. C is only the overhead absorbed.
▶ Starts at Q25 (49:18)
Starts at Q25 (49:18) · by Study with Prashna. Tap the picture to open it on YouTube.
Solutions follow the official Cambridge mark schemes. Videos are from other YouTube channels. Paper codes read component / series / year: M/J = May/June, O/N = October/November. Past-paper questions © UCLES, reproduced for classroom practice.