The question asks which costs of a new railway count as private costs and which as external costs in cost–benefit analysis.
A private cost is a cost paid by the decision-maker, here the cost of building the line.
An external cost is a cost to third parties who are not part of the decision, such as noise to people living near the route.
So the answer is C.
A, B and D give the wrong label to the building cost or to the noise.