Cambridge A2 Level Accounting 9706 · 4.2 Standard costing

Q32 · 9706/41/M/J/24 Q2

Worked solution from the Cost and management accounting (A Level) Theory (Paper 4) booklet, Part 2 of 4.

Q329706/41/M/J/24original Q2Structured · 25 marks
Question 2 from 9706/41/M/J/24

Worked solution

(a)(i)

Sales price variance $55 000 adverse ÷ 11 000 units = $5 adverse per unit.

= $5 adverse per unit [1]

Actual selling price = $210 − $5 = $205 [1]

(a)(ii)

Add up the cost variances (the two material variances are favourable, labour efficiency is adverse):

Net adverse cost variances = 57 750 − 4 290 − 8 360 = $45 100 [1]

Extra price needed per unit = $45 100 ÷ 11 000 = $4.10 [1]

Unit selling price = $210 + $4.10 = $214.10 [1]

(a)(iii)

Material usage variance $8 360 favourable ÷ standard price $7.60 = kilos saved.

8 360 ÷ 7.60 = 1 100 kilos saved [1]

Standard kilos = 11 000 units × 4 = 44 000 [1]

Actual kilos used = 44 000 − 1 100 = 42 900 kilos [1]

(a)(iv)

Material price variance $4 290 favourable ÷ actual kilos 42 900.

4 290 ÷ 42 900 = $0.10 per kilo lower than standard [1]

Actual price = $7.60 − $0.10 = $7.50 per kilo [1]

(a)(v)

Labour efficiency variance $57 750 adverse ÷ standard rate $10.50 = extra hours.

57 750 ÷ (10.50 × 11 000 units) [1]

= 0.5 hours extra per unit [1]

Actual hours per unit = 3 + 0.5 = 3.5 hours [1]

(b)

Write: a flexible budget statement. [1]

(c)

Write any four reasons:

To help cost control and cost reduction. [1]

To provide a benchmark against which actual results are compared. [1]

To help with decision making. [1]

To motivate staff. [1]

(d)

Advise: points for and against (up to 3 marks each), then a decision with a comment.

For: arithmetical errors are avoided and calculation is faster. [1]

Figures recalculate automatically when a variable changes, so 'what if' questions can be asked. [1]

Security can be improved with passwords and information is easily shared between departments. [1]

Against: some staff may not be familiar with the software. [1]

The budgets are still only as good as the estimates made, and errors can be made in data entry or formulae. [1]

Security of data may be compromised. [1]

Decision: write a clear decision supported by a comment. [1]

KEY IDEAWork backwards from each variance (variance ÷ standard rate or price) to find actual quantities, prices and hours.
TOTAL 25 marks

Official mark scheme

Mark scheme for 9706/41/M/J/24 question 2
VIDEO
▶ Whole paper

Video solution of the whole paper · by A LEVEL ACCOUNTING. Tap the picture to open it on YouTube.

Solutions follow the official Cambridge mark schemes; marks are shown in grey. Videos are from other YouTube channels. Paper codes read component / series / year: M/J = May/June, O/N = October/November. Past-paper questions © UCLES, reproduced for classroom practice.